Sunday, December 16, 2018
Solid Waste Fund Balance Rises to $4.37 Million
San Angelo's City Council authorized City Manager Daniel Valenzuela to amend the solid waste contract with Republic Service allowing a reduction in acceptable recycling materials. Republic committed to the following recyclables at City Council in March 2015.
Council reduced this list to:
This is the second change in the contract for Republic Services. The first removed recycling collection from weekly to every other week and increased bulk collection from quarterly to the week opposite recycling. The second reduces the kind of material allowed.
The City did not remove the recycling penalty charge of 50 cents of a month when it reduced the frequency of recycling and has been silent on this fee as the types of recycling are reduced.
The Finance Department updated Council on the Solid Waste Department's fiscal year close. Solid Waste made a nearly $900,000 profit.
Finance Director Tina Dierschke failed to mention the Solid Waste Fund Balance of nearly $4.4 million at the end of the fiscal year. It turns out trash is highly profitable for Republic and the City of San Angelo.
Update 12-21-18: The Standard Times ran the city's position on the recycling change. The 50 cent recycling charge remains in place according to the story.
Tuesday, December 11, 2018
City Removes Financial Report Documents from Website
The City's Finance Department received recognition at City Council for Excellence in Financial Reporting on 12-11-18. The proclamation stated the award:
"demonstrates “a constructive spirit of full disclosure to clearly communicate its financial story.”
Our citizens want assurances their city government manages their tax dollars with the utmost efficiency, effectiveness and transparency. Earning this honor five years in a row gives the public a high level of assurance that is indeed the case. Interested taxpayers are invited and encouraged to go to the City’s website to read our award-winning audit report.
Oddly, the week before this recognition the Finance Department removed monthly financial report documents from its website. The City no longer has any 2018 or 2017 Bluebook documents available for the public to access.
Older documents from 2015-2016 remain accessible to the public. I wrote Mayor Brenda Gunter and blind copied every member of City Council. Not one council person responded after being informed of this move away from openness and transparency.
The documents remain inaccessible on the city's website.
While not on the city's website the 2018 Bluebook accounting documents are available here. (added to this post on 12-26-18)
Update 2-15-23: The City was honored yet again for its annual financial audit. It's the city's 9th Certificate of Achievement for Excellence in Financial Reporting.
Saturday, December 08, 2018
City Seeks Bids for 2019 Street Sealcoating
The City set a December 11, 2018 deadline for contractors to submit bids for 2019 street sealcoating. The only bidder to attend the pre-bid conference was CSA Materials, a division of ReeceAlbert. The city provided contractors a map of the targeted streets, which can be seen above.
September and October rains took their toll on city streets. Many San Angelo city streets are beyond rehabilitation via sealcoating due to base failure. Public Works staff told former City Councilman Marty Self the city would not throw money away sealcoating streets that needed greater restoration work. If Mr. Self drove through the targeted neighborhoods what would he find?
Saturday, December 01, 2018
Benedetti Phoenix Buyback Date Looms
City Manager Daniel Valenzuela provided information on the city's road repair portfolio in his 2017 State of the City address. Valenzuela highlighted the city's Benedetti Phoenix which enables city crews to rehabilitate certain San Angelo streets. :
Asphalt Recycler Picks up Steam: Once proficient on the operation of the new recycling machinery, the crews will move to N. Chadbourne from 29th Street to 43rd Street. Chadbourne Street from Loop 306 to 29th will be reconstructed in 2018-2019 and the asphalt recycler will extend the pleasurable driving experience to 43rd Street. From there, the City will systematically work its way across town with a focus on the roadways identified as needing mill-and-overlay in the 2015 street assessment.A related e-mail from Assistant Operations Director Patrick Freyrich stated:
Asphalt Recycling: The new Benedetti Phoenix asphalt recycler that Council approved in November 2016 arrived in San Angelo in July 2017 and City crews began the training process on Rio Concho Drive shortly thereafter. Through research and discussions with engineers and users across multiple countries, asphalt recycling provides an option to improve the condition of our street surfaces as well as provide a smoother, more pleasant drive for the traveling public. At just a fraction of the per-square-yard cost of the alternative mill-and-overly or reconstruction options, asphalt recycling could allow the City to improve roadways that may not have been repaired beyond seal coating every eight years. Our crews have been working hard learning the proper operation and techniques that meet our expectations. The learning curve has been greater than anticipated, but we are being meticulous about ensuring we get a great final product and still expect the asphalt recycling project to meet our expectations. In addition to saving bond money that can be reassigned to other reconstruction projects, this process is expected to provide a better ride for travelers and a roadway that is protected from further deterioration.In the first week of operation city staff experienced at least one fireball and two members of the HIPAR crew quit. City documents reported:
Our first accident happened on Day 3. As the crew was performing the end-of-day cleaning, diesel was sprayed on the plant that was still too hot from the day’s operation and ignition occurred. The fireball engulfed an employee that was cleaning the screed augers, but thankfully no serious injuries occurred.
At the beginning of Day 5, two of the original crew (screed operator and hand operator) opted to leave the HIPAR crew. The reason given by both was due to the amount of smoke from the operation.
We had substantial flame-ups that came from, it was later discovered, our end-of-day shutdown procedures. Apparently, at the end of the day, diesel was liberally sprayed on the Recycler components to rid them of asphalt. This resulted in a lot of diesel running onto the roadway and soaking in. As such, when the Preheater and Recycler crossed those areas the residual diesel ignited and flames engulfed the machines. The hand crew worked hard to cover the enflamed areas with sand, but it was a losing battle. The end-of-day cleaning changed from using diesel as a cutting agent to scraping the bulk of the asphalt off by hand and lightly misting the augers, mill, and plant with diesel to break down any remaining asphalt.During Spring 2018 budget sessions City Council discussed staffing issues with the Benedetti Phoenix and implemented pay changes intended to retain trained staff. The city took another crack at utilizing the equipment. Crews worked on Era Street from May-July.
City documents show their specialized street crew used the Benedetti Phoenix only four of the last thirteen months. Statistics indicate the city did only 0.6 lane miles far less than projected breakeven amount.
City Council will undertake whether to keep the asphalt recycling equipment or ask the manufacturer to buy it back. That decision needs to be made in December 2018.
The public deserves to hear from responsible parties City Manager Daniel Valenzuela and Executive Director of Public Works Ricky Dickson on this item.
Update 1-13-19: City staff plan to provide Council an update on the Benedetti machine. They made this commitment at the 1-8-19 City Council meeting.
Update 1-19-19: Staff recommends City Council exercise the buyback provision in their upcoming meeting.
Friday, November 23, 2018
City's Agreement with MedHab Nears Expiration
The City of San Angelo's economic development agreement with MedHab LLC will expire January 1, 2019. City Council approved the $3.6 million incentive package on January 3, 2012 and the approved the contract seven months later. The city had high hopes for significant job creation which can be seen in estimated impact of 75 new jobs (with up to 227 total).
The City projected an annual economic impact of $9.9 million.
The 2014 Annual Report for the Development Corporation stated:
Under that agreement, MedHab LLC will locate its production operation in San Angelo, create between 75 and 227 full-time qualifying positions, and relocate its offices to the Incubator Annex at 2009 W. Beauregard Ave., which was accomplished in December 2012.To date MedHab has not had the projected impact on San Angelo employment. The company accepted three years of free rent but has not accessed any other incentive provided in the contract.
Several months ago both the Development Corporation and City Council took up MedHab in executive session. City officials shared nothing in regard to those discussions. What happens on January 1, 2019? Does MedHab, with its promising fall detection device for seniors, walk away from the City of San Angelo?
Saturday, November 17, 2018
Mayor Gunter Snubbed by Finance Staff
On October 20, 2018 Mayor Brenda Gunter asked city staff to present information on how the city performed in its just closed fiscal year. Finance Director Tina Dierschke expressed reluctance to present unaudited numbers in her reply. Four days later Dierschke did just that for the city's Development Corporation.
"Good morning, Board. I'm going to present your year end unaudited financial statements to you this morning."--Tina Dierschke, Finance Director
It's not clear why city staff ignored the Mayor's request for November 6th and 20th City Council meetings, but they have.
Update 12-8-18: Staff will present preliminary financial results for fiscal year ended 9-30-18 at the upcoming City Council meeting on 12-11-18.
Saturday, November 03, 2018
Mayor Asks, City Staff Ignores
Mayor Brenda Gunter made a clear request of San Angelo city staff during the October 16, 2018 Council meeting. It was not recorded in the minutes or acted upon for the November 6, 2018 City Council meeting.
Mayor Gunter asked staff to present the financial results from the just closed fiscal year. This item is not on the November 6th agenda as requested. The Mayor made a clear request the minutes fail to document in that section or under future agenda items.
The Water Enterprise Fund Balance rose to $10.3 million as of 9-30-18. That's 158 days of budgeted water revenue. The city said its target is 75 days. Other water fund balances total $20.5 million. That does not include the Lake Nasworthy fund of $14 million. With massive runoff the last two months the City's water supply is the healthiest I've ever seen.
The Solid Waste Fund Balance rose to $4.3 million. Council will deal with the solid waste contract in Executive Session. Republic Services requested to walk back its recycling commitments.
Council makes strategic budget decisions and should hear the results of their actions prior to the completion of the fiscal audit. I applaud Mayor Gunter's request for timely feedback. Time will show if staff intend to deliver.
Update 11-16-18: Once again city staff ignored the Mayor's request (as reflected in the November 20 City Council agenda.)
Subscribe to: