The data center with the highest likelihood of being built is coming to town.  Cipher Digital's representative Lee Bratcher will be at the Veribest School Cafeteria for a Town Hall Meeting on Monday, November 30th at 5:00 pm.  

Bratcher finally found Veribest, after confusing it with Wall at a Tom Green County Commissioners' meeting.

He told Commissioners that Cipher Digital would not ask local officials to sign non-disclosure agreements, but economic development details are hidden behind legal protections as "consultations with attorneys."  

Bratcher noted that Cipher would negotiate a 380 agreement if the County wanted a say on aspects of their development.

The City of San Angelo had a 380 agreement on their Closed Agenda for the last three meetings.  It may or may not be Cipher's Colchis 1 gigawatt data center site (that is just outside city limits).

Cipher Digital operated Bitcoin Mining operations across West Texas and is converting those to high performance computing data centers.  Thus, they have a track record in the region.  

Lee Bratcher of the silver tongue joined Cipher in early 2026. The press release for his hiring noted: 
Mr. Bratcher worked closely with policymakers, regulators, and industry leaders in the energy and data center spaces, contributing to the research and development of two pieces of legislation passed during the 87th Texas Legislative Session, as well as two additional bills enacted during the 88th Session and signed into law. 
Bratcher dropped the name Bill Blevins, Cipher's Head of Grid Strategies: 
Blevins joins Cipher from the Electric Reliability Council of Texas (“ERCOT”), where he served as Director of Grid Coordination. That announcement came in June. 
The project received conditional approval from ERCOT.  Cipher gave AEP $17 million to prepare their grid connection and that work could be well underway.   Cochis updated timeframe for energizing is 2028-2029.  

If the money is there to fund the project I'm sure Cipher is itching to start.  That said, Cipher's stock has taken a beating and is just off its 52 week low of $5.07 and far from it's high of $30.14.


A public meeting is also a big change given Cipher's very quiet operation to date.  Turn out has been significant at other townhall meetings (Emergent and Beacon).  Will Cipher's Colchis site garner the same animus?  